THE RENOVATION
Welcome Page
Once upon a time

Part 1 Part 2
The Early days
Part 1 Part 2
Utilities
Life's little luxuries
Septic Tank Install
Electricity arrives
The first cottage
Part 1 Part 2
Part 3 Part 4
The second cottage
Clearing Out
Attic conversion
First Floor
Living Room
Kitchen / Dining
Swimming Pool
Part 1 Part 2
Later modifications
The Farmhouse
Bathroom Study
Bedroom Hallway
Kitchen Living Room
Music room Attic Bed
Exterior and Garden
Part 1 Part 2 Part 3
Part 4 Part 5
Before and After
REFERENCE PAGES
RETURN TO FRONTPAGE

THE FARMHOUSE - Music Room

Last year we said we were adding a music room to the farmhouse. After a short winter break we were back into the swing of things by March. February was pretty busy with visiting househunters, and my bones just don't operate properly below 10 degrees anymore! Perhaps it was also the thought of removing 2 feet of compacted tuf and paving stones from the barn floor that was making my body a little reluctant.

Anyway, one early March morning, we bravely stood at the entrance armed with spades and wheelbarrow and surveyed the scene, the only way of getting warm was to start. Sticking my spade into the ground, shuddering into the first paving slab by accident, and jarring my elbow in the process I declared that this was as good a place as any to start! I won't bore you with the details, but ten days later we had it all cleared, carefully ensuring that the large stones which also underpinned the walls remained untouched. We now had an excavated barn floor, tuf flooring for the exterior woodstore and a mountain of stones filling the last remaining empty barn!
The next job was to remove the old barn floor on the first floor - this had been breakfast, lunch and dinner to numerous generations of woodworm, who were eventually going to discover how well a Waterford stove works! The easiest way to remove it was with a chainsaw, dumping the whole sorry mess into the ground floor. (Yes I know I should be wearing a hard hat!) Then followed another afternoon with the trusty wheelbarrow.
New foundations were laid around the circumerence of the original walls to take the new beton cellulaire walls and the beams for the raised timber floor. Because the barn is underground at the rear, the only way to provide underfloor ventilation was via pipework leading from above ground level - so no, the pipework is not for yet another fosse septique! The beton cellulaire was 15cm thick to provide good all around insulation for the room. It is pretty easy to erect and the walls took under a week to finish. Although below ground, the rear wall has always been remarkably dry so in this instance we dispensed with a drainage channel, although note that all of the walls had a dpc installed.
The floor beams were then set in place (20cm for a 4 metre span) onto the wall foundations (not forgetting the dpc), although these were also additionally supported by pillars in the centre of each alternate beam for additional rigidity. The base of the beams were then stapled with a network of galvanised wire (you can also use chicken wire) to support the 200mm underfloor insulation). Electrics were completed then the floorboarding began.
New flooring was put in on the barn first level (we used waterproof chipboard sheets 22mm), after dropping three of the beams by 10 cm. to provide some feature on the ceiling. The beams were a friendly 50cm apart so proved no problem for the chipboard apart from the usual problem of getting the whole think approximately level, and allowing for the dropped beams with chevron inserts.

To plasterboard in between all of them would have been too much for the spacious look that we were trying to achieve, no exposed beams would have made the ceiling look featureless, so we compromised. In order to reduce the amount of joint filling and skimming we chose to mount the plasterboard panels along the length of the room, (ie in the same direction as the rails which is not normal) this meant having to be very precise in locating the rails exactly at the point where the plasterboard sheets would join. It also meant the suspentes (pictured left below) had to be spaced away from the dropped beams in order to take the rails. Ultimately this was all worth the effort in the time it saved during the finishing stage and made shaping the plasterboard around the exposed beams that much easier. Once all the suspentes had been put in place then the insulation was positioned (yuk) then finally the rails were clipped into place. A week of plasterboarding, the usual finishing chores and the job was completed by mid May - Whoo!
The finished article. The pine floor was stained down with Golden Oak which give a beautiful warm orange glow to the floor, and, for the first time in this renovation, we decided to wallpaper the walls, choosing a design which looks like old plaster - very fitting. Time for a rest now - maybe - with only one room to go and our parents deciding not to visit this year. Why then do I get this feeling of forboding???

 

Top of Page